The project budget has been finalized.Additionalwork has been discovered that was not planned for in the budget or projectscope. () could provide thefund to cover the newly discovered
A. Contingencyreserve
B. Projectprofit
C. Managementreserve
D. Specialfund
查看答案
Establishingaproject()involveslistenmilestones,activities,anddeliverableswithintendedstartandfinishdates,ofwhichtheschedulingofemployeesmaybeanelement
A. costmanagementplan
B. riskmanagementplan
C. soopemanagementplan
D. managementschedule
To ensure the project team provides thefunctionality the customer expects in a new piece of software, the projectmanager ask the customer for sign-off on the design criteriA.These documents
A. technicalspecifications
B. performancespecifications
C. productdescriptions
D. qualityassurance
The Develop ProjectManagement Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ()
A. ProjectScopeStatement
B. .ProjectManagementPlan
C. Forecasts
D. ProjectCharter
A line manager provides you with three estimates for his activity inyour PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would
A. 4weeks
B. 5weeks
C. 6weeks
D. 7weeks