The Develop ProjectManagement Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ()
A. ProjectScopeStatement
B. .ProjectManagementPlan
C. Forecasts
D. ProjectCharter
查看答案
A line manager provides you with three estimates for his activity inyour PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would
A. 4weeks
B. 5weeks
C. 6weeks
D. 7weeks
()are the four major activities of software configuration management.①configuration identification ②statement report③change control④preparation of requirement document ⑤configuration auditing
A. ①②③④
B. ①②④⑤
C. ①②③⑤
D. ②③④⑤
Cloud computing is a style of computing in which dynamically scalabled often () resources are provided as a service over the internet
A. real
B. fixed
C. actual
D. virtualized
() is the use of computing resources(hardware and software) that a delivered as a service over a network(typically the Internet).
A. Virtualization
B. Internetofthings
Cloudcomputer
D. Cloudcomputing