题目内容

To ensure the project team provides thefunctionality the customer expects in a new piece of software, the projectmanager ask the customer for sign-off on the design criteriA.These documents

A. technicalspecifications
B. performancespecifications
C. productdescriptions
D. qualityassurance

查看答案
更多问题

The Develop ProjectManagement Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ()

A. ProjectScopeStatement
B. .ProjectManagementPlan
C. Forecasts
D. ProjectCharter

A line manager provides you with three estimates for his activity inyour PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would

A. 4weeks
B. 5weeks
C. 6weeks
D. 7weeks

()are the four major activities of software configuration management.①configuration identification ②statement report③change control④preparation of requirement document ⑤configuration auditing

A. ①②③④
B. ①②④⑤
C. ①②③⑤
D. ②③④⑤

Cloud computing is a style of computing in which dynamically scalabled often () resources are provided as a service over the internet

A. real
B. fixed
C. actual
D. virtualized