A line manager provides you with three estimates for his activity inyour PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would
A. 4weeks
B. 5weeks
C. 6weeks
D. 7weeks
查看答案
()are the four major activities of software configuration management.①configuration identification ②statement report③change control④preparation of requirement document ⑤configuration auditing
A. ①②③④
B. ①②④⑤
C. ①②③⑤
D. ②③④⑤
Cloud computing is a style of computing in which dynamically scalabled often () resources are provided as a service over the internet
A. real
B. fixed
C. actual
D. virtualized
() is the use of computing resources(hardware and software) that a delivered as a service over a network(typically the Internet).
A. Virtualization
B. Internetofthings
Cloudcomputer
D. Cloudcomputing
Several riskresponse strategies are available. (75)the risk simply gives another party responsibility for itsmanagement,it does not eliminate risk.
Avoiding
B. Mitigating
C. Accepting
D. Transferring