Which of the following is incorrect about specifications?
A. The specifications involved a specific brand-identified product can be regarded as“open”.
B. The use of standard specifications has met with only limited acceptance because of uniqueness of the projects.
C. Specifications are one of the most critical components of contracts.
D. Standard specifications are mostly acceptable in highway projects.
查看答案
Which of the following item is correct about an offer (bid)?
A. In construction, owners generally require bids submitted in a particular format.
B. An offer is always made to multiple entities.
C. An offer can always be practically comprehensive.
D. Offer period of the subs’ bids to the GC are ALWAYS consistent with the one in prime contract.
Which of the following item is correct about an acceptance?
A. “Acceptance” means an agreeing by conduct to the offer of another.
B. Keeping silence can be a good practice to reject offers of another.
C. If a subcontract is mentioned in a prime bid (between the GC and the owner), that subcontract is legally binding to the owner.
Which of the following is INCORRECT?
A. DSC clauses provide guiding principles for parties to deal with the site conditions significantly different from contract documents.
B. Normally in DSC clauses, the owner or A/E are not eligible to investigate DSC promptly.
C. DSC clauses normally address time and cost adjustment clauses.
D. Normally in DSC clauses, the GC shall promptly notify the owner when DSC exists on site.
First, the owner looks for the architect-engineer performing their design. Second, the owner delivers the drawings (when available) to the general contractor. Thirdly, the general contractor performs the construction work accordingly. This project costs less than 5,000 USD and less than three months. Which one of the FIDIC contract templates would be the most suitable for this particular job?
A. “Yellow Book”
B. “Silver Book”
C. “Green Book”
DBO contract