Which of the following is INCORRECT?

A. DSC clauses provide guiding principles for parties to deal with the site conditions significantly different from contract documents.
B. Normally in DSC clauses, the owner or A/E are not eligible to investigate DSC promptly.
C. DSC clauses normally address time and cost adjustment clauses.
D. Normally in DSC clauses, the GC shall promptly notify the owner when DSC exists on site.

查看答案
更多问题

First, the owner looks for the architect-engineer performing their design. Second, the owner delivers the drawings (when available) to the general contractor. Thirdly, the general contractor performs the construction work accordingly. This project costs less than 5,000 USD and less than three months. Which one of the FIDIC contract templates would be the most suitable for this particular job?

A. “Yellow Book”
B. “Silver Book”
C. “Green Book”
DBO contract

Which of the following is an open specification?

A. The initial flow rate of the kitchen ventilator should be set at more than 60 L/ min …
B. The kitchen ventilator should be made by Haier

Which of the following item is required FIRST for the cost of lump-sum estimating?

A. Indirect costs
B. Equipment
C. Material (Quantity takeoff )
D. Markup

Which of the following item is NOT directly related to bid ethics?

A. Bid Shopping
B. Increase sub-bid quotes to GC after the award of prime bid
C. Inflation
D. Bid Rigging