Which of the following item is correct about an acceptance?
A. “Acceptance” means an agreeing by conduct to the offer of another.
B. Keeping silence can be a good practice to reject offers of another.
C. If a subcontract is mentioned in a prime bid (between the GC and the owner), that subcontract is legally binding to the owner.
查看答案
Which of the following is INCORRECT?
A. DSC clauses provide guiding principles for parties to deal with the site conditions significantly different from contract documents.
B. Normally in DSC clauses, the owner or A/E are not eligible to investigate DSC promptly.
C. DSC clauses normally address time and cost adjustment clauses.
D. Normally in DSC clauses, the GC shall promptly notify the owner when DSC exists on site.
First, the owner looks for the architect-engineer performing their design. Second, the owner delivers the drawings (when available) to the general contractor. Thirdly, the general contractor performs the construction work accordingly. This project costs less than 5,000 USD and less than three months. Which one of the FIDIC contract templates would be the most suitable for this particular job?
A. “Yellow Book”
B. “Silver Book”
C. “Green Book”
DBO contract
Which of the following is an open specification?
A. The initial flow rate of the kitchen ventilator should be set at more than 60 L/ min …
B. The kitchen ventilator should be made by Haier
Which of the following item is required FIRST for the cost of lump-sum estimating?
A. Indirect costs
B. Equipment
C. Material (Quantity takeoff )
D. Markup