During your execution of the previous project, you had difficulties getting signoffs against the scope definition even though you delivered what the customer had specified. For the better execution for future projects,which process will you pay more atten

A. Performance Reporting。
B. Scope Verification。
C. Scope Definition。
D. Administrative Closure。