《河北旅游质量提升行动计划(2018—2020年)》对我省旅游业质量提升工程提出了一系列具体措施,重点是围绕哪几项?
During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope of work . The project manager had access to correspondence about the project before the charter was signed and remembers that the projec
A. let the sponsors know of the stakeholders' request .
B. evaluate the impact of adding the scope of work .
C. tell the stakeholders the scope cannot be added .
D. add the work if there is time available in the project schedule .
The sponsor and other in your organization are repeatedly requesting changes . When you try to implement some of the changes, you discover the current contract does not include a budget for evaluating changes . What should you do?
Ask senior management for more money from the company's reserve .
B. Tell the sponsor there is no budget for changes in the project .
C. Negotiate with the sponsor to decide how to remedy this problem .
D. Take the matter directly to your contracting/legal department .