During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope of work . The project manager had access to correspondence about the project before the charter was signed and remembers that the projec
A. let the sponsors know of the stakeholders' request .
B. evaluate the impact of adding the scope of work .
C. tell the stakeholders the scope cannot be added .
D. add the work if there is time available in the project schedule .