In general, the bestlong-lasting approach to settling project conflict is the () approach.
A. Problemsolving
B. Compromise
C. Withdrawal
D. Smoothing
查看答案
The work breakdown structurecomprises several levels of decomposition of the total project.The lowest level of definition is always the () .
A. planning
B. element
C. subtask
D. workinginterface
The most expensive phase oflife cycle costing is () .
A. Termination.
B. Appliedresearch.
C. Production
D. Operationsandsupport
The project budget has been finalized.Additionalwork has been discovered that was not planned for in the budget or projectscope. () could provide thefund to cover the newly discovered
A. Contingencyreserve
B. Projectprofit
C. Managementreserve
D. Specialfund
Establishingaproject()involveslistenmilestones,activities,anddeliverableswithintendedstartandfinishdates,ofwhichtheschedulingofemployeesmaybeanelement
A. costmanagementplan
B. riskmanagementplan
C. soopemanagementplan
D. managementschedule