题目内容

The work breakdown structurecomprises several levels of decomposition of the total project.The lowest level of definition is always the () .

A. planning
B. element
C. subtask
D. workinginterface

查看答案
更多问题

The most expensive phase oflife cycle costing is () .

A. Termination.
B. Appliedresearch.
C. Production
D. Operationsandsupport

The project budget has been finalized.Additionalwork has been discovered that was not planned for in the budget or projectscope. () could provide thefund to cover the newly discovered

A. Contingencyreserve
B. Projectprofit
C. Managementreserve
D. Specialfund

Establishingaproject()involveslistenmilestones,activities,anddeliverableswithintendedstartandfinishdates,ofwhichtheschedulingofemployeesmaybeanelement

A. costmanagementplan
B. riskmanagementplan
C. soopemanagementplan
D. managementschedule

To ensure the project team provides thefunctionality the customer expects in a new piece of software, the projectmanager ask the customer for sign-off on the design criteriA.These documents

A. technicalspecifications
B. performancespecifications
C. productdescriptions
D. qualityassurance