题目内容

In your project, if the benefit cost ratio is greater than 1, it means that ().

A. the ratio of profits to cost is greater than 1
B. the ratio of revenue to cost is greater than 1
C. you should select this project from all other competing alternatives
D. none of the above

查看答案
更多问题

A precise description of a deliverable is called a ().

A. specification
B. baseline
C. work package
D. work breakdown structure element

All of the following is true for a project baseline EXCEPT ().

A. it is the original approved plan
B. it includes approved scope changes
C. it is useful in detecting project variances
D. it is useful in preparing the WBS

在巴纳德看来,组织的存在取决于( )

A. 协作系统平衡的维持
B. 组织成员的责任一致
C. 组织的需求
D. 协作系统的失衡

Quality control should be performed ().

A. when the product of the project is completed to ensure that no defects exist
B. throughout the project life cycle
C. during the closeout phase but before final acceptance by the customer
D. as desired by the quality assurance department

答案查题题库