Quality control should be performed ().
A. when the product of the project is completed to ensure that no defects exist
B. throughout the project life cycle
C. during the closeout phase but before final acceptance by the customer
D. as desired by the quality assurance department
激活菜单栏的快捷键是( )。
A) F10
B) F4
C) F5
D) Ctrl
Your technical team leader, Ted, proposed an action that would overall project quality with a minor cost increase. The project control officer, Sun Ha, recommended an approach that would shorten the project schedule, but reduce product features. Increasing quality and accelerating the schedule are critical form your point of view. Although you believe that Ted and Sun Ha could learn from each other, they typically like to agree to disagree. You need a conflict resolution method that provides a long-term resolution. You decide to use which one of the following approaches ?()
A. Confronting
B. Problem solving
Compromise
D. Smoothing
Due to cuts in funding, your project has been terminated. The scope verification process ().
A. should be delayed until the project is completed
B. should determine the correctness of the work results
C. should establish and document the level and extent of completion
D. will form the basis of the project audit