题目内容

关于填筑作业面要求的表述,错误的是( )。

A. 地面起伏不平时,应按水平分层由低处开始逐层填筑,不得顺坡铺填
B. 分段作业面长度,机械施工时段长不应小于150m,人工施工时段长可适当减短
C. 作业面应分层统一铺土、统一碾压,严禁出现界沟,上、下层的分段接缝应错开
D. 已铺土料表面在压实前被晒干时,应洒水润湿

查看答案
更多问题

You are in the close project process.You are engaged in the activity to settle and close some contract agreements established for the project.Which of the following activities are you into ?()

Administrative closure
B. Contract closure
C. Project executing
D. Planning

You are assigned to be the project manager in the middle of the project. The project is within tolerances for the baseline, but the customer is not happy with the performance of the project. What is the FIRST thing you should do ?()

A. Discuss it with the project team
B. Recalculate baselines
C. Renegotiate the contract
D. Meet with the customer

You are the project manager responsible for developing a software application based on customer requirements.As the customer requirements keep changing frequently,what tool can you use to conduct integrated change control of your project ?()

A. Project selection methods
B. Additional planning
Corrective action
D. Project management information system

In a project, two team members were using different versions of WBS. Team members could not know the status of project management plan documents. Project manager should FIRST check ().

A. configuration management system
B. work performance information
C. change control system
D. information gathering and retrieval systems

答案查题题库