题目内容

You are in the close project process.You are engaged in the activity to settle and close some contract agreements established for the project.Which of the following activities are you into ?()

Administrative closure
B. Contract closure
C. Project executing
D. Planning

查看答案
更多问题

You are assigned to be the project manager in the middle of the project. The project is within tolerances for the baseline, but the customer is not happy with the performance of the project. What is the FIRST thing you should do ?()

A. Discuss it with the project team
B. Recalculate baselines
C. Renegotiate the contract
D. Meet with the customer

You are the project manager responsible for developing a software application based on customer requirements.As the customer requirements keep changing frequently,what tool can you use to conduct integrated change control of your project ?()

A. Project selection methods
B. Additional planning
Corrective action
D. Project management information system

In a project, two team members were using different versions of WBS. Team members could not know the status of project management plan documents. Project manager should FIRST check ().

A. configuration management system
B. work performance information
C. change control system
D. information gathering and retrieval systems

在房建项目中,人们经常用每平方米的平均造价,来估算拟建项目的总造价。这种估算是以下哪种情况的例子?()

A. 专家判断
B. 自下而上估算
C. 参数估算
D. 三点估算