You are the project manager responsible for developing a software application based on customer requirements.As the customer requirements keep changing frequently,what tool can you use to conduct integrated change control of your project ?()

A. Project selection methods
B. Additional planning
Corrective action
D. Project management information system

查看答案
更多问题

In a project, two team members were using different versions of WBS. Team members could not know the status of project management plan documents. Project manager should FIRST check ().

A. configuration management system
B. work performance information
C. change control system
D. information gathering and retrieval systems

在房建项目中,人们经常用每平方米的平均造价,来估算拟建项目的总造价。这种估算是以下哪种情况的例子?()

A. 专家判断
B. 自下而上估算
C. 参数估算
D. 三点估算

After project control, organizational process assets are updated. Wherever checklists are used, the completed checklists should become part of the ().

A. project's records
B. project files
C. project quality management plan
D. lessons learned documentation

In your project,there is:50% probability for $40000 profit,50% probability for $25000 loss.What is the expected profit in your project ?()

A. $32500
B. $25000
C. $7500
D. -$7500(i.e. loss of $7500)