题目内容

An Example: Clause 1(DSC): additional compensation for DSC Clause 2(Disclaimer): the subs ______ on the boring logs Court: DSC takes precedence

查看答案
更多问题

Missing DSC can be dangerous: No right of ______ unless a differing site conditions exists Thus, the right to relief based on DSC is not an ______ right:Inexperienced contractors may assume to receive extra cost and time automatically – however, courts place the risk on contractors given the absence of the DSC clause

MULTIEMPLOYER WORK SITES DEFINED by OSHA Four categories of employers______ employer.______ employer. ______ employer. ______ employer.

No-damages-for-delay clauses (NDD) Limited to an EOT but no cost adjustment EVEN in instances where the owner’s acts or failure to act (An ______ clause) Judicial attitudes on NDD: mixed

Which one of the following items is NOT an element for the establishment of type I (one) differing site condition (DSC).

A. Two geological conditions on the same site are generically different.
B. The contract documents must be specific about the geological condition.
C. The actual condition materially differs from the condition stipulated in the contract.