Which one of the following items is NOT an element for the establishment of type I (one) differing site condition (DSC).
A. Two geological conditions on the same site are generically different.
B. The contract documents must be specific about the geological condition.
C. The actual condition materially differs from the condition stipulated in the contract.
查看答案
Which of the following item(s) is INCORRECT about insurance?
Additional parties are sometimes named as “additional named insureds.”
B. Worker’s compensation and employer’s liability insurance contract assume the liability imposed on the insured contractor employer when an employee is injured or killed.
C. Insurance premium rate modifiers of worker’s compensation policies are normally based on the financial capability of GC.
D. Flat premium payment for the duration of the project (for builder’s risk insurance) is the prevalent method in use in the industry.
Which one is NOT common exclusions of the public liability policies of an insurance contract?
A. On-site operations.
B. Explosions.
C. Structural Collapse.
D. Underground utilities.
To properly assign culpability for an infraction of the standards on multiemployer worksites, current OSHA policy establishes four categories of employers on such sites. The following definition is CORRECT:
A. Creating employer: The employer whose employees are exposed to hazards.
B. Controlling employer: The employer who is responsible, by contract or through actual practice, for safety and health conditions on the work site, that is, the employer who has the authority for ensuring that the hazardous condition is corrected.
C. Exposing employer: The employer who actually creates the hazard.
Which of the following is INCORRECT about the concept “delay?”
A. The critical path is a path of work activities that contains no float.
B. Compensable delays refer to delays that do not result from the defaults of neither the owner nor the GC.
C. An as-planned schedule network reflects the planned progress and the deadline for accomplishment of the project.
D. A schedule update network is used to reflect the competition status of the project at the points in time of the periodic updates.