An output of scope definition is ().

A. work breakdown structure (WBS)
B. resource breakdown structure (RBS)
C. project scope statement
D. schedule delays control plan

查看答案
更多问题

Activity duration estimate inputs include all of the following EXCEPT ().

A. resource requirements
B. projeet document updates
C. activity lists
D. constraints

Which of the following is a direct project cost ?()

A. Lighting and heating for the corporate office
B. Workers compensation insurance
C. Piping for an irrigation project
D. A and B

Which of the following is a common characteristic of most project life cycle descriptions ?()

A. Cost and staffing are low at start,higher towards the end of implementation.and drop rapidly as the project nears completion
B. The probability of successfully completing the project is highest at the start of the project
C. Stakeholders have the most influence on the final characteristics of the product at the end of the project
D. Risk and uncertainty are lowest at the start of the project

You are in the build phase of the project.But it has run into several unanticipated problems.Several risks have surfaced which you had not anticipated earlier.The project is over-budget and behind schedule.What should you do ?()

A. Create updates to risk response plan
B. Create a revised project plan
C. Perform risk response audits
D. Perform updated risk identification and analysis