Which of the following is a common characteristic of most project life cycle descriptions ?()
A. Cost and staffing are low at start,higher towards the end of implementation.and drop rapidly as the project nears completion
B. The probability of successfully completing the project is highest at the start of the project
C. Stakeholders have the most influence on the final characteristics of the product at the end of the project
D. Risk and uncertainty are lowest at the start of the project
查看答案
You are in the build phase of the project.But it has run into several unanticipated problems.Several risks have surfaced which you had not anticipated earlier.The project is over-budget and behind schedule.What should you do ?()
A. Create updates to risk response plan
B. Create a revised project plan
C. Perform risk response audits
D. Perform updated risk identification and analysis
The project quality assurance characterizes the followings except ().
A. assessing overall project performance
B. checking the quality of specific project deliverables
C. provided to the project management team
D. provided to the project sponsor
In your project, you have started doing human resource planning and are studying the interpersonal relationships among the candidates who are being considered for the project team. Some factors you consider include: What type of formal and informal reporting relationships exist amongst the candidates for the project team What are the candidate's job descriptions What are the supervisor-subordinate relationships What cultural or language differences will affect working relationship between team members What levels of trust and respect currently exist All this information will be available as part of ().
A. enterprise environmental factors
B. organization hierarchy
C. informal reporting relationships
D. all of the above
The high-level project schedule constraints have just been determined.What project management process group are you in ?()
A. Initiating
B. Planning
C. Executing
D. Monitoring and controlling