题目内容

While preparing your risk responses, you realize that you have not planned for know risk events . You need to make adjustments to the project to compensate for unknown risk events . These adjustments are based on your past project experience when unknown

Apply a general contingency to try to compensate .
B. Document the unknown risk items and calculate the expected monetary value based on probability and impact that result from the occurrence .
C. Determine the unknown risk events and the associated cost, then add the cost to the project budget as reserves .
D. Add a 10% contingency .

查看答案
更多问题

During project closure a project sponsor complains that the project did not increase the department's knowledge of Java programming and therefore, the project is not complete . The customer has accepted the project . The project manager determines that al

A. begin project closure .
B. re-plan the project to include the new objective .
C. meet with the team to discuss the find a resolution .
D. get the project stakeholders involved to help resolve the issue .

Your organization is having a difficult time managing all of its project . You have been asked to help senior management get a better understanding of the problems . What do you do FIRST?

A. Meet with individual project managers to get a better sense of what is happening .
B. Send a formal memo to all project managers requesting their project plans .
C. Meet with senior managers to all project help them develop a new tracking system for managing projects .
D. Review the project charters Gantt charts for all projects .

You are a new project manager for company B . You previously worked for company A that had an extensive project management practice . Company B has its own procedures, but you are more familiar with those company A . You should:

A. use the practices from company A but include any forms from company B .
B. use the forms from company B and begin to instruct them on ways to upgrade their own .
C. talk about changes to the change control board of company B .
D. interact with other in an ethical way by sharing the good aspects of company A's procedures .

Who determines the requirements of a new project?

A. Customer .
B. Stakeholders .
C. Project manager .
D. Senior management .