如果在一个课程注册系统中,定义了类CourseSchedule和类Course,并且在类CourseSchedule中定义了方法Add(c:Course)和方法Remove(c:Course),那么类CourseSchedule和类Course之间的是一种 () 的关系。
查看答案
In project management, a () is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。
A. schedule
B. activity
C. Plan
D. contractor
Project manager believes thatmodifying the project scope may provide added value for the customer. Theproject manager should () .
A. changethescopebaseline
B. contactthecustomertodetermineifthechangeaddsvalue
C. callameetingofthechangecontrolboard
D. changetheproject’sobjectives
Software engineers apply the principles of software engineering to the design, development, (72) ,testing, and evaluation of the software and systems that make computers or anything containing softwar
A. Requirement
B. construction
C. service
D. maintenance
Those items are often estimated in terms of resource () , budget and duration.Linked by dependencies and scheduled events.
A. finding
B. balance
C. allocation
D. distribution