Software engineers apply the principles of software engineering to the design, development, (72) ,testing, and evaluation of the software and systems that make computers or anything containing softwar
A. Requirement
B. construction
C. service
D. maintenance
查看答案
Those items are often estimated in terms of resource () , budget and duration.Linked by dependencies and scheduled events.
A. finding
B. balance
C. allocation
D. distribution
The key benefit of()is that it provides guidance and direction on how the project costs will be managed throughout the project.
A. planCostManagement
B. ControlCost
C. EstimateCost
DetermineBudget
A proj ect manager is called to an informal meeting with thecustomer and a problem is raised. Thisproblem has major implications for theproject manager's company, but the customer wants
A. tellthecustomerthathewillnotaddressanyproblemsbecausethisisonlyaninformationexchangemeetmg
B. ellthecustomerthattheproblemisnotsufficientlydefinedtodeterminetheappropriateaction
C. ollectasmuchinformationontheproblemwithoutcommittinghiscompanytoasolution
D. givethecustomerarangeofsolutionsthatmightbeacceptabletohisCompany
A schedule is commonly used in project planning and project portfolio management.() on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work,
A. Essences
B. Elements
C. Purposes
D. Issues