You are a project manager working through the determine budget process. Your project scope statement provides for a budget of $75,000, but it was prepared last year prior to your detailed analysis. Which of the following tools and techniques will you NOT use?你是项目经理,正处于制定预算过程。你手里的项目范围说明书给出了一个75000美元的预算,但是那是去年在你没有进行详细分析之前的一个预算。下面的各种工具和技术,你将不会用到:
A. Cost aggregation 成本汇总
B. Reserve analysis.储备分析
C. Funding limit reconciliation 资金限额调节
D. Cost of Quality 质量成本
查看答案
You can use the following methods to calculate earned value, except可以使用下列各种方法计算挣值,除了()。
A. Forward calculation algorithm 顺推计算法
B. Weighted milestone method 加权里程碑法
C. Fixed formula method固定公式法
D. Percentage of completion method完成百分比法
The project performance report includes the following figures: PV = 110, EV = 100, AC = 120, and the total budget is 150. What is the cost variance? 项目绩效报告中包括如下数字:PV=110, EV=100,AC=120,总预算为150。成本偏差是多少?
A. -20
B. -10
C. 10
D. 20
If the earned value is $300000, the actual cost is $355000, the planned value is $370000, and the project's progress performance index is如果挣值是300000美元,实际成本是355000美元,计划价值是370000美元,项目的进度绩效指数是()。
A. 0.85
B. 1.25
C. 1.16
D. 0.81
EV(BCWP)=350,AC(ACWP)=400,PV(BCWS)=325,SV=? SPI=? 如果EV(BCWP)=350,用AC(ACWP)=400,PV(BCWS)=325,进度偏差(SV)和进度绩效指标(SPI)为多少?
A. +25;0.875
B. +25;1.077
C. -50;0.875
D. +50;1.077