You can use the following methods to calculate earned value, except可以使用下列各种方法计算挣值,除了()。
A. Forward calculation algorithm 顺推计算法
B. Weighted milestone method 加权里程碑法
C. Fixed formula method固定公式法
D. Percentage of completion method完成百分比法
查看答案
The project performance report includes the following figures: PV = 110, EV = 100, AC = 120, and the total budget is 150. What is the cost variance? 项目绩效报告中包括如下数字:PV=110, EV=100,AC=120,总预算为150。成本偏差是多少?
A. -20
B. -10
C. 10
D. 20
If the earned value is $300000, the actual cost is $355000, the planned value is $370000, and the project's progress performance index is如果挣值是300000美元,实际成本是355000美元,计划价值是370000美元,项目的进度绩效指数是()。
A. 0.85
B. 1.25
C. 1.16
D. 0.81
EV(BCWP)=350,AC(ACWP)=400,PV(BCWS)=325,SV=? SPI=? 如果EV(BCWP)=350,用AC(ACWP)=400,PV(BCWS)=325,进度偏差(SV)和进度绩效指标(SPI)为多少?
A. +25;0.875
B. +25;1.077
C. -50;0.875
D. +50;1.077
Project cost management includes all of the following processes except 项目成本管理包括下列所有过程,除了()。
A. Estimate resources 估算资源
B. Estimate cost 估算成本
C. Budget making制定预算
D. Control cost 控制成本