Which of the following item is CORRECT?

A. In general, contract ADR stages that the parties agree to go through after they go to court.
B. Mediation is a consensual process and thus cannot be stipulated as a compulsory step in ADR.
C. Some countries legally make DAB as a compulsory process for dispute resolution in construction.
D. All the decisions in ADR are final.

查看答案
更多问题

The following item is NOT an element for the establishment of differing site conditions (DSC).

A. Two parts of the conditions in the same site are substantially different.
B. The contract documents must have indicated a physical condition.
C. Actual conditions are materially different from what is stipulated in the contract.

Which of the following is NOT the reason for denying differing site condition claims?

A. Lack of notice
B. Difference is not material
C. High turnover rate of construction crews
D. Failure to conduct an adequate pre-bid site inspection

Which of the following item is INCORRECT?

A. In the US, construction safety performance largely improved after 2001.
B. OSHA requires the employers to keep / preserve fatality / accident records.
Currently, site inspection performed by OSHA should be accompanied with the employers or its representative.

Which of the following item is INCORRECT?

A. FIDIC Redbook 2017 requires that the contractor shall submit to the Engineer for information a health and safety manual.
B. Non-conformance of safety code can be regarded as breach of a contract (if provisions are available).
C. “Whistle-blower” provisions require employers’ duty of quality audit.
D. In general, the contract should reflect that the owner is eligible to perform safety inspections.