A project manager and her team worked together to develop a work breakdown structure.However,it seems project team members are doing work that is not included in the work breakdown structure. The purpose of a work breakdown structure is to:
A. guide the cost estimate for a project,not how the work is done。
B. provide senior management with a high level view of the project scope。
C. include the work required to create the products of the project。
D. Include the total project scope or all of the work that must be done to complete the project。
查看答案
中国独特的自然地理条件,可以很好地用来检验产生于西方的理论是否有普适性。()
A new project manager is planning a complex hardware installation project. The team consists of 15 people who are experts in their fields. The project manager does not want to manage the project in the detailed level. How far should he decompose the work?
As small as possible because the work is complex。
B. As large as possible because he is dealing with experts。
C. To 1000-hour tasks because he is dealing with experts 。
D. To about 80-hour tasks because it is proper for check-in period。