A new project manager is planning a complex hardware installation project. The team consists of 15 people who are experts in their fields. The project manager does not want to manage the project in the detailed level. How far should he decompose the work?
As small as possible because the work is complex。
B. As large as possible because he is dealing with experts。
C. To 1000-hour tasks because he is dealing with experts 。
D. To about 80-hour tasks because it is proper for check-in period。
What is the major aspect of scope verification?
A. It ensures the project deliverable is completed on time。
B. It makes sure the project is on track by ensuring the customer's acceptance of the deliverable。
C. It shows the deliverable meets specifications。
D. It provides a chance for differences of opinion to come to light。
基于中国问题的研究,对经济学的一般理论没有太大贡献。()