Which of the following item is incorrect?

A. Compensable delay indicates the delay is resulted from the owner’s fault.
B. Excusable delay means the delay is resulted from the factors not resulted from both parties.
Compensable delay indicates the GC is not entitled to both EOT and profit.
D. Excusable delay makes GC entitled to EOT but generally not entitled to profit.

查看答案
更多问题

Suspensions Establish the authority of the contracting officer (CO) to order the contract to suspend, delay, or interrupt all the work______ cessation; leads to waste (ex. ______ of the crew) Contractor shall protect, store and secure The responsibility of the GC, then ______ should be negotiated

Terminations Terminations – cessations is ______ ______ / ______ terminations Force ______

The following item is INCORRECT about suspension or termination.

A. In general, suspensions do not leads to waste of resources, such as crew idling
B. Suspensions mean temporal cessation of work
C. Terminations indicate permanent cessations of the work
D. Terminations can be resulted from owner’s default

The specifications describe in writing the quality of the materials and the standards of ______ required. These documents serve four important functions One of the most critical ______ of the contract ______ tools Describing the work to be accomplished and defining the ______ of the participant's A ______ for competitive bidding or contract negotiation

答案查题题库