Terminations Terminations – cessations is ______ ______ / ______ terminations Force ______

查看答案
更多问题

The following item is INCORRECT about suspension or termination.

A. In general, suspensions do not leads to waste of resources, such as crew idling
B. Suspensions mean temporal cessation of work
C. Terminations indicate permanent cessations of the work
D. Terminations can be resulted from owner’s default

The specifications describe in writing the quality of the materials and the standards of ______ required. These documents serve four important functions One of the most critical ______ of the contract ______ tools Describing the work to be accomplished and defining the ______ of the participant's A ______ for competitive bidding or contract negotiation

Which of the following item concerning “contract type” is correct?

A fixed price contract contains the most risk for the buyer.
B. Cost reimbursable contracts potentially offer sellers the highest profit.
C. Lump sum contracts potentially offer sellers the highest profit.
D. Unit price contracts are illegal in many jurisdictions.

To transfer most of the cost risks to the contractor, the client may use a ___________ contract.

A. cost plus award fee
B. cost plus incentive fee
C. cost plus fixed fee
D. fixed price