题目内容

EAC is a periodic evaluation of: 完工估算是对______的定期评估。

A. Cost of work complete完成工作的成本
B. Value of work performed已完成工作的价值
C. Anticipated total cost at project completion 项目完工时的预期总成本
D. What it will cost to finish the job完成工作还需要花的成本

查看答案
更多问题

CV=0,SV<0 , Which do you want to focus on? CV=0,SV<0 ,问要关注哪个?

A. Cost saving 成本节约
B. Ahead of schedule 进度提前
Cost overrun 成本超支
D. Behind of schedule 进度落后

Project managers need to consider the following costs when making project decisions, except 项目经理进行项目决策时,需要考虑以下各种成本,除了()。

A. Indirect cost 间接成本
B. Fixed cost 固定成本
C. Viriable cost 可变成本
D. Sunk cost沉没成本

The cost deviation of the project is equal to项目的成本偏差等于()。

A. EV-AC
B. EV-PV
C. AC-EV
D. AC-PV

The cumulative CPI has been shown to be relatively stable after what percentage of project completion?在完成项目工作多少个百分比后,累计成本绩效指数相对稳定?

A. 5% to 10%
B. 15% to 20%
C. 25% to 35%
D. 50% to 75%

答案查题题库