CV=0,SV<0 , Which do you want to focus on? CV=0,SV<0 ,问要关注哪个?
A. Cost saving 成本节约
B. Ahead of schedule 进度提前
Cost overrun 成本超支
D. Behind of schedule 进度落后
查看答案
Project managers need to consider the following costs when making project decisions, except 项目经理进行项目决策时,需要考虑以下各种成本,除了()。
A. Indirect cost 间接成本
B. Fixed cost 固定成本
C. Viriable cost 可变成本
D. Sunk cost沉没成本
The cost deviation of the project is equal to项目的成本偏差等于()。
A. EV-AC
B. EV-PV
C. AC-EV
D. AC-PV
The cumulative CPI has been shown to be relatively stable after what percentage of project completion?在完成项目工作多少个百分比后,累计成本绩效指数相对稳定?
A. 5% to 10%
B. 15% to 20%
C. 25% to 35%
D. 50% to 75%
The opportunity cost is机会成本是()。
A. The price of a new project 开展一个新项目而必须付出的代价
B. The cost we pay when we give up something to get something else.为从事某项经营活动而放弃另一项经营活动的机会,或利用一定资源获得某种收入时所放弃的另一种收入
C. Virtual costs that do not need to be considered when making decisions 进行决策时无需考虑的虚拟成本
D. All costs to be spent in the future未来要开支的所有成本