某分包商承包了某专业分项工程,分包合同中规定:工程量为2400m3;合同工期为30d,6月11日开工,7月10日完工;逾期违约金为1000元/d。该分包商根据企业定额规定:正常施工情况下(按计划完成每天安排的工作量),采用计日工资的日工资标准为60元/工日(折算成小时工资为7.5元/h)。延时加班,每小时按小时工资标准的120%计;夜间加班,每班按日工资标准的130%计。该分包商原计划每天安排20人(按8h计算)施工,由于施工机械调配出现问题,致使该专业分项工程推迟到6月18日才开工。为了保证按合同工期完工,分包商可采取延时加班(每天延长工作时间,不超过4h)或夜间加班(每班按8h计算)两种方式赶工。延时加班和夜间加班的人数与正常作业的人数相同。[问题] 若夜间施工每天增加其他费用100元.每天需额外增加多少费用?
查看答案
·You will hear a conversation between two employees of a company which is going to move its premises.·For each question 23-30, mark one letter (A, B or C) for the correct answer.·After you have listened once, replay the recording. Which department will be the last to move
A. Customer Services
B. Sales
C. Public Relations
·You will hear a conversation between two employees of a company which is going to move its premises.·For each question 23-30, mark one letter (A, B or C) for the correct answer.·After you have listened once, replay the recording. The company will spend most money on
A. special new office furniture.
B. new technology.
C. recruiting a designer.
某分包商承包了某专业分项工程,分包合同中规定:工程量为2400m3;合同工期为30d,6月11日开工,7月10日完工;逾期违约金为1000元/d。该分包商根据企业定额规定:正常施工情况下(按计划完成每天安排的工作量),采用计日工资的日工资标准为60元/工日(折算成小时工资为7.5元/h)。延时加班,每小时按小时工资标准的120%计;夜间加班,每班按日工资标准的130%计。该分包商原计划每天安排20人(按8h计算)施工,由于施工机械调配出现问题,致使该专业分项工程推迟到6月18日才开工。为了保证按合同工期完工,分包商可采取延时加班(每天延长工作时间,不超过4h)或夜间加班(每班按8h计算)两种方式赶工。延时加班和夜间加班的人数与正常作业的人数相同。[问题] 若采取夜间加班方式赶工,加班期内白天施工平均降效5%,夜间施工平均降效15%,需加班多少天(计算结果四舍五入取整)
·You will hear a conversation between two employees of a company which is going to move its premises.·For each question 23-30, mark one letter (A, B or C) for the correct answer.·After you have listened once, replay the recording. At the new premises there will be
A. a staff gym.
B. a better staff canteen.
C. extra meeting rooms.