题目内容

Managing Priorities Most of us are kept so busy managing our own lives that we can’t imagine how top executives manage the work of thousands of people and millions of dollars and still have time to eat, sleep, and live. (9) But in talking about how they run their lives and companies, they do tend to focus on common themes. Unfortunately, popular time management courses are not the answer. Even the founder of the time management movement, Alec Mackenzie, agrees that few people who take his courses stick with the techniques and really benefit from them. (10) Like many other company executives, Alcoa’s CEO, Paul O’Neill, lists "quality" among his highest priorities~ But at the very top of his list is a surprise, "safety. " Alcoa leads its industry in safety and has been cutting its injury records by 50% every five years. O’Neill feels that to make an operation truly safe, you must understand it perfectly and make sure that the operation isn’t inefficient in any way that would encourage dangerous shortcuts. (11) One principle that works for many busy managers is the 80/20 rule, (12) —20% of its customers. A business that can identify the 20% and what they order can focus attention on those products. Illinois Tool Works, for example, used the 80/20 rule to identify which of its thousands of products it should concentrate on as it realigned its manufacturing processes. In an other instance, Office Club, a discount office-supplies supermarket, decided to carry 2,200 items instead of its competitors’ 5,000 because it found that 85 % of its sales came from only 650 core items. Every CEO has techniques for making time in a hectic schedule, (13) Some count on expert secretaries to arrange their time; others learn to walk out of a meeting if participants are late. According to management expert, Peter Drucker, (14) A. You will find different things at the top of CEOs’ priority lists B. Establishment of priorities is a key factor in managerial and organizational effectiveness C. There is no one secret that successful executives share D. the most important skill for setting priorities and managing time is simply learning to say No E. In other words, quality and safety go hand in hand F. doing important thinking while jogging or showering or flying to meetings G. Defined as a ranking of goals, objectives, or activities in order of importance, priorities play a special role in planning H. which states that 80% of a company’s business generally comes from a small group

查看答案
更多问题

某工程项目施工阶段,业主与监理单位、施工单位分别签订了监理合同、施工合同。在主体施工阶段(12层框架一剪力墙结构),施工之前监理工程师对现场施工单位存放的一批钢筋进行了检查。施工单位出具了钢材的试验报告(合格),专业监理工程师同意使用该批材料进行施工。在施工过程中监理工程师现场旁站监督,并对某检验批完成后进行了验收,对其主控项目和一般项目经抽样检验合格,监理工程师签署该检验批质量合格。当施工到某层(框架)时,施工单位没有通知监理工程师又进场一批同规格的钢筋(同上一批钢筋为同一厂家).,监理工程师发现后,要求施工单位出具书面材料,施工单位出具进场材料的出厂合格证、技术说明书、材质化验单等质量保证文件(齐全)。施工单位认为长期使用该厂家材料且该厂信誉较好,所以该批材料可以免检,由于工期较紧,施工单位取得专业监理工程师同意指令使用该批材料进行施工。 下列属于现场质量检查中开工前要检查的内容是( )。

A. 是否具备开工条件
B. 对重要的工序或对工程质量有重大影响的工序,应严格执行“三检”制度
C. 检查成品有无保护措施以及保护措施是否有效可靠
D. 施工中凡是隐蔽工程必须检查认证后方可进行隐蔽措施

某施工单位(乙方)与某建设单位(甲方)签订了建造无线电发射试验基地施工合同。合同工期为38天。由于该项目急于投入使用,在合同中规定,工期每提前 (或拖后)1天奖(罚)5 000元。乙方按时提交了施工方案和施工网络进度计划(图5-13),并得到甲方代表的同意。 实际施工过程中发生了如下几项事件。 事件1:在房屋基槽开挖后,发现局部有软弱下卧层。按甲方代表指示,乙方配合地质复查,配合用工为10个工日。地质复查后,根据经甲方代表批准的地基处理方案,增加工程费用4万元,因地基复查和处理使房屋基础施工延长3天,人工窝工15个工日。 事件2:在发射塔基施工时,因发射塔坐落位置的设计尺寸不当,甲方代表要求修改设计,拆除已施工的基础,重新定位施工。由此造成工程费用增加1.5万元,发射塔基础施工延长2天。 事件3:在房屋主体施工中,因施工机械故障,造成工人窝工8个工日,房屋主体施工延长2天。 事件4:在敷设电缆时,因乙方购买的电缆质量不合格,甲方代表令乙方重新购买合格电缆。由此造成敷设电缆施工延长4天,材料损失费1.2万元。 事件5:鉴于该工程工期较紧,乙方在房屋装修过程中采取了加快施工的技术措施,使房屋装修施工缩短3天,该项技术措施费为0.9万元。 其余各项工作持续时间和费用均与原计划相符。 对于合同执行者而言,合同跟踪的对象有( )。

A. 承包的任务
B. 工程小组或分包人的工程和工作
C. 业主和其委托的工程师的工作
D. 设计部门的设计变更工作
E. 供应商的供应进度和质量

建设单位与施工单位按照《建设工程施工合同(示范)文本》签订了施工承包合同。该工程包含两个子项工程,估计工程量甲项为4 000m3,乙项为2 000m3,合同单价甲项为220元/m3,乙项为560元/m3,工程预付款额度为合同价的12%,主要材料和构件所占比重为60%。同时,施工合同中规定:(1)设备由建设单位采购,施工单位安装; (2)建设单位原因导致的施工单位人员窝工,按18元/工日补偿,建设单位原因导致的施工单位设备闲置,按下表中所列标准补偿; 设备闲置补偿标准表机械名称台班单价(元/台班)补偿标准机械名称台班单价(元/台班)补偿标准大型起重机1060台班单价的60%自卸汽车(8 t)458台班单价的50%自卸汽车(5 t)318台班单价的40% (3)施工过程中发生的设计变更,其价款按建标[2003]206号文件的规定以工料单价法计价程序计价(以直接费为计算基础),间接费费率为10%;利润率为5%,税率为3.41%。 该工程在施工过程中发生以下事件。 事件1:建设单位采购的设备没有按计划时间到场,施工受到影响,施工单位一台大型起重机、两台自卸汽车(载重5t、8t各1台)闲置5天,工人窝工86工日,工期延误5天。 事件2:某分项工程由于建设单位提出工程使用功能的调整,须进行设计变更。设计变更后,经确认直接工程费增加18 000元,措施费增加2 000元。 上述事件发生后,施工单位及时向建设单位造价工程师提出索赔要求。 该工程预付款的起扣点为( )万元。

A. 160
B. 165
C. 170
D. 175

某施工企业通过投标获得了某住宅楼的施工任务,地下18层、地下3层,钢筋混凝土剪力墙结构;业主与施工单位、监理单位分别签订了施工合同、委托监理合同。施工单位(总包单位)将土方开挖、外墙涂料与防水工程分别分包给专业性公司,并签订了分包合同。 施工合同中说明:建筑面积23 420m2,工程工期450天,2003年8月1日开工,2004年11月25日竣工,工程造价3 165万元。 合同约定结算方法:合同价款调整范围为业主认定的工程量增减、设计变更和洽商;外墙涂料、防水工程的材料费,调整依据为本地区工程造价管理部门公布的价格调整文件。 合同价款包括成本和酬金两部分,双方在合同专用条款内约定成本构成和酬金的计算方法属于分包工程合同价款中的( )。

A. 固定价格
B. 可调价格
C. 成本加酬金
D. 成本价

答案查题题库