You have been informed by the Customer of a small change to the original scope. It is a small effort as compared to the total project and you need the good-will for a huge project. You will:

A. Refuse to do the work
B. Agree to do the work and bill him later。
C. Do the work and bill him later
D. Assess the cost and schedule impact and tell them you will decide later。

查看答案
更多问题

好的声誉及口碑作为一种信号可以让大家了解经理的能力,从而付给经理更高的工资。()

The following is most false:

A. The lowest level of the WBS could also be called a work package。
B. A WBS dictionary can be used to hold the descriptions of the various work components。
C. A contractor's WBS and contractual WBS(CWBS)基本上是相同的。
D. The work packages in a WBS can be broken down still further。

A client has asked you to add scope of work to the project is under budget and a little ahead of schedule. What should you do ?

Approve the change。
B. Let the client know the effects of the change on the project。
C. Ask approval from the sponsor for making the change。
D. Get approval from the configuration change board。