Which of the following item is INCORRECT?

A. Differing site conditions can be referred as “concealed conditions.”
B. If“ the furnished geotechnical report is NOT part of the contract documents "is shown in the bidding documents, the GCs should be aware that they could probably bear geotechnical risks.
C. The information in reports of physical site conditions can be used to determine the quotes in bids.
D. For grassroots projects, DSC condition provisions are not important at all.

查看答案
更多问题

Which of the following item is very unlikely to be classified as “Force Majeure (FM)”?

A. Civil war in Libya
B. Coordination of subcontractors
C. Earth quake in Taiwan
D. Typhoon in Guangdong

Which of the following item is CORRECT about termination?

A. Convenience termination provisions address the defaults of GC.
B. Default termination provisions refer to the owner’s termination without disclosing reasons.
C. The owner can involve the third party to complete the work if the original contract is terminated.
D. Provisions dealing with payment result from termination is not critical because GC and the owner can always bargain.

Which of the following is correct?

A. GC should always be liable for a delay.
B. Owners are gods therefore, owners should not be assumed liable for a delay.
C. Owners‘ support can be critical to the performance of a GC.

Which of the item is CORRECT?

A. It’s perfectly fine if no liquidated damage provision presents in construction contracts.
B. Allocating safety managerial roles and responsibilities is one of the major purpose of safety provisions.
C. Insurance provisions protect obligee; bond provisions protect the subject against risks.
D. One of the main purpose of insurance is to cover the loss results from non-performance of the obligor.