Which of the following is INCORRECT about the stakeholders?
A. Normally, a GC coordinates most of the construction work.
B. Stakeholders’ considerations are different.
C. An architect-engineer always conduct in-house design rather than subcontract to special consultants.
D. A broker contractor means the contractor who outsource most of the construction work except supervision, coordination, and management.
查看答案
The delivery mode of the abovementioned project is similar to _______________
A. Integrated Project Delivery (IPD)
B. Engineering-Procurement-Construction
C. Design-Build-Operate-Maintain (DBOM)
Design-Bid-Build (DBB)
Which of the following item is CORRECT?
A. Seasonality is not a risk source to construction.
B. Local condition is one of the major risk source that makes mgmt. procedure difficult to be implemented.
C. Most of the stakeholders in construction are fast in applying management procedures.
D. Employee turnover is low in construction.
In general, ________ desires fixed price contracts rather than cost reimbursable contracts.
A. The owner
B. No one
C. The contractor
Which of the following is CORRECT?
A. DSC is unimportant to civil projects and therefore, related clauses are dispensable in the contract.
B. In a contract, conflicts between DSC clauses and other conflicts are impossible.
C. Type II DSC clauses are always shown in the contracts.
DSC clauses normally refer cost / time adjustment clauses.