某软件开发项目,预算为40万元,计划在40个工作日内完成。当项目进展到30个工作日时,项目经理对项目进行了绩效评估,结果是:项目完成当期计划进度的70%,花费了23万,按此绩效还需投入大约()万元才能完成该项目。
A. 10
B. 12
C. 19
D. 21
The communication management plan determines the information and communications needs of the stakeholders.In the following statements related to communication management plan,()is false.
A. the communication management plan is contained in,or is a subsidiary plan of,the project management plan
B. the communication management plan can be formal or informal,highly detailed or broadly framed,and based on the needs of the project
C. the communication management plan organize and summarize the information gathered,and present the results of any analysis as compared to the performance measurement baseline
D. the communication management plan can include guidelines for project status meetings,project team meetings,e-meetings,and e-mails
简答题 论多项目的资源管理在很多企业中,同时实施的项目越来越多,项目经理们经常同时负责多个项目。项目越多,管理就越复杂,因此企业越来越多地遇到多项目管理的问题。多项目的范围既包括相关联的多个项目,也可以是相互没有关联的多个项目。多项目管理区别于单个项目管理已成为一种新的管理模式,它要对所有涉及的项目进行评估、计划、组织、执行与控制。如何协调和分配现有项目资源,以获取最大的收益则成为多项目管理的核心内容。请围绕“多项目的资源管理”论题,分别从以下三个方面进行论述:1.简要叙述你同时管理的多个信息系统工程项目,或你所在的组织中同时开展的多个项目的基本情况,包括多项目之间的关系,项目的背景、目的、周期、交付产品等相关信息,以及你在其中担任的主要工作。2.结合你所参与的多项目管理实践,从多项目的资源管理原则、方法、内容及要点等方面论述如何进行多项目的资源管理。3.结合你参与过的项目中遇到的资源管理的问题,阐述如何从企业层面提供多项目资源管理的保障和支持。
软件测试不再是一种仅在编码阶段完成后才开始的活动。现在的软件测试被认为是一种应该包括在整个开发和维护过程中的活动。测试工作往往采用V模型来进行,可以从()阶段就开始编写测试计划。
A. 立项
B. 需求分析
C. 设计
D. 编码